What is the total workhours needed for a crew of 10 people that works 8 hour days to install 10 tons of rebar at a rate of 0.10 tons/Whr?
1) 32 Whrs
2) 4,000 Whrs
3) 1,000 Whrs
4) 3,200 Whrs
5) 985 Whrs