A contractor has just received a labor intensive project contract to produce and supply 700 units of a certain product. While pricing a contract, its project pricing department has predicted that producing the first unit requires 500 hours. The pricing department believes that a 75 percent learning curve is justified for this type of work. Determine the total cost of this project assuming that a fully burdened labor hour costs $65.