A car manufacturer has just implemented a new Master Production Schedule (MPS) to manage production over the next three months. Which of the following is NOT typically included in a Master Production Schedule?
O Production rate for each week and day
O Specific production targets for each product line
O Supplier delivery schedules for critical components
O Detailed demand forecasting for the upcoming fiscal year