The Company has a problem. Tom. Who was in charge of a critical control account, Quit and destroyed most of his cost records. All that could be salvaged were the following bits of information.
BAC=120000
Cumulative earned value 40000,
cumulative cost variance=-10000,
cumulative schedule variance=1000,
estimate to complete=86000.

Help reconstruct the status of tom's control account by determining the following items.
A. Percent Complete
B. Budget (Cumulative)
C. Actuals (Cumulative)
D. EAC
E. Variance at Completion
F. CPI
G. TCPI
H. Calculate a projected EAC using the standard independent EAC formula of EAC=AC+ETC, where ETC=Work Remaining/CPI