Consider the following project
Activity’s Name Immediate predecessor Time to complete the job
A 3
B 2
C B 4
D C 3
E A, C 1
F D, E 1
1. Draw a network diagram representing this project.
2. Identify the critical path.
3. What is the minimum time needed to complete this project​