Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following estimates:

Total estimated direct labor-hours 44,000
Total estimated fixed manufacturing overhead cost $ 224,400
Estimated Variable manufacturing overhead per direct labor-hour $ 5.00


Recently, Job P951 was completed with the following characteristics:

Total direct labor-hours 100
Direct materials $ 750
Direct labor cost $ 4,400


The total job cost for Job P951 is

Question 10 options:

$5,410


$1,760


$5,150


$6,160



Answer :

Other Questions