In network scheduling terminology, an __activity__________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete.
12 Which type of task dependency is described as follows: Task A must start before Task B can finish.
a. Finish-to-Start (FS)//
b. Start-to-Finish (SF)
c. Finish-to-Finish (FF)
d. Start-to-Start (SS)



Answer :