Calculate EVM metrics for the following test problems: Plan at End of 2nd Quarter: Tasks 1, 3, 5 and 6 should be completed, Tasks 2 and 4 should be 96 percent complete, and Task 7 should be 51 percent complete. Results at End of 2nd Quarter: Tasks 1, 3, 5, and 6 have been completed, Task 2 is 50 percent complete, Task 4 has not been started, and Task 7 is 10 percent complete. $137,500 has been charged to the project.