A work crew of 3 people requires 3 weeks and 2 days to do a certain job. How long would it take a work crew of 4 people to do the same job if each person of both crews works at the same rate as each of the others. [Note: each week contains six work days]

Thanks for the help!



Answer :

20  days per 3 people         for 4 people


20/3 * 4 = 26 & 2/3 days