Which of the following statements regarding planning & scheduling is not correct?
A. ADM (arrow diagramming method) was the initial CPM (critical path method) algorithm but now is outdated due to development of the PDM (precedence
diagram method).
B. The development of the project's CPM (critical path schedules) schedule determines the PoC (Path of Construction).
C. Gantt charts (or bar charts) are a common way to communicate schedule information.
D. A good schedule will have "CPM integrity", meaning it is completely logically-linked and has limited use of constraints.



Answer :